School Update 26th June 2009

This is the main classroom with its Magima tiles The roof of first classroom block has now been tiled and the floors have been concreted, internal walls plastered and the doors hung. The administration block in the distance suffered some damage during the rainy seasons and it will need to be repaired and then roofed with […]

Update on the Namanditi School

During this year’s dry season the first two classroom block has been roofed with clay pantiles from the Magima village ceramics factory. A second classroom building has its brickwork completed and  the roof timbers in place. An administration building and maize mill house also have the brickwork completed and the toilet block foundations have been […]