School Update 26th June 2009
The roof of first classroom block has now been tiled and the floors have been concreted, internal walls plastered and the doors hung. The administration block in the distance suffered some damage during the rainy seasons and it will need to be repaired and then roofed with tiles from Magima. The brickwork of the second classroom block is complete but the windows need to be fitted and the roof tiled before the internal walls are plastered and the floors laid.
In addition we need to roof the toilet block. It is still hoped that this work can be finished in time for the school to open for a small first intake of pupils in September but as always we need to raise more funds. The area around the buildings and play ground will also have to be fenced, in keeping with local regulations. Raising the funds to complete this work is our focus for the summer.